Project Details
WeGo Public Transit hired BCMason Group to replace the sewer line at their Nestor Facility. To start, we removed railroad tracks and ties as well as perimeter fencing. We then had the soil tested by an environmental specialist to ensure it’s suitable for the new sewer pipe. We installed approximately 1000 feet of 8-inch sewer pipe and structures into the existing line. This project also required concrete and asphalt paving.
​
OUR ROLE
General Contractor
​
PROJECT COST
Under $1M
​
COMPLETION DATE
November 2023